Adani Green Energy has sought reimbursement for its initial investment after withdrawing from two wind power projects in Sri Lanka, valued at $442 million.
This decision came after the newly elected National People’s Power (NPP) government in Sri Lanka sought to renegotiate the power purchase agreement, aiming for a lower cost of power than what was agreed upon by the previous administration.
โก Project Timeline & Financials
-
May 2024: Sri Lankaโs previous administration signed a 20โyear Power Purchase Agreement (PPA) with Adani Green Energy for two wind farms (Mannar & Pooneryn), totalling 484โฏMW, at a tariff of 8.26โฏยข/kWh.
-
Jan 2025: The new government under President Dissanayake revoked the agreed tariff and set up committees to renegotiate, targeting below 6โฏยข/kWh.
-
Feb 2025: Adani announced its withdrawal from the project after having invested ~USโฏ$5โฏmillion in pre-development costs.
๐ Regarding โReimbursementโ
-
No formal reimbursement deal has been reported. Adani invested ~$5โฏmillion in preparatory studies but did not proceed. They exited and expressed openness to renegotiate, not to refund expenditures.
-
Sri Lankan officials havenโt announced any plan or demand for reimbursement. Their priority has been restructuring tariff termsโor seeking new investorsโnot recovering sunk costs .
Also Read : ITSME Activeren : Activate | My itsme
๐ Current Status:
-
The government remains open to renewing the project under acceptable tariffs (~5โ7โฏยข/kWh), and discussions continue.
-
Environmental and legal petitions were dropped after Adaniโs withdrawal, with no claims for damages or reimbursement noted.
-
Adani reassured it remains ready to invest up to USDโฏ1โฏbillion in Sri Lankaโs renewables if conditions align.
โ Bottom Line
-
No reimbursement agreement has been publicized.
-
Adaniโs exit absorbed ~USDโฏ5โฏmillion in pre-development costsโno refund.
-
Sri Lanka is now focused on finding a viable tariff and potentially partnering with Adani or another investor.
-
If your inquiry concerns recouping losses or compensation, thereโs currently no framework or public negotiations on that front.